Strayer BUS 375 Midterm Exam Part 2
Question 1
Which of the following is NOT one of the recommended guidelines for developing useful work package estimates?
Question 2
Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?
Question 3
Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognizing?
Question 4
Refining estimates may be necessary for a number of reasons. For example, resource shortages, in the form of people, equipment, or materials, can extend original estimates. This is a good example of
Question 5
Refining estimates may be necessary for a number of reasons. For example, a manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project and meet the needs of the customer is an example of
Question 6
Which of the following is NOT true in regard to the level of detail estimates should contain?
Question 7
Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. Which of the following methods is he using?
Question 8
The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as
Question 9
Which of the following is NOT one of the bottom-up approaches to estimating project time and cost?
Question 10
Richard is collecting estimates for a house that he will have the funding to build in 12 months. Which of the following factors does Richard need to consider in regard to the quality of these estimates?
Question 11
Which of the following top-down methods is used when projects closely follow past projects in regard to the features and costs of those features and result in costs being assigned by percentages to major segments of the project?
Question 12
Which of the following is a good condition for bottom-up estimating?
Question 13
What is the relationship between organizational culture and estimating?
STATUS
Question 14
Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of
Question 15
System documentation cannot end until three days after testing has started. This is an example of which kind of lag?
Question 16
Which of the following will correctly calculate the total slack in an activity?
Question 17
Which of the following is NOT one of the basic rules to follow when developing project networks?
Question 18
When translated into a project network, a work package will become
Question 19
Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of
Question 20
Which of the following correctly calculates the late start for an activity?
Question 21
________ activities must be completed immediately before a particular activity.
Question 22
The backward pass in project network calculations determines all of the following EXCEPT
Question 23
The critical path in a project network is the
Question 24
Which of the following correctly calculates the early finish for an activity?
Question 25
If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a